Welcome. Here you will find relevant information about the project. The information on this page will be updated on a regular basis – check back regularly.

DOCUMENTS

These documents will be updated on a regular basis.


ESTIMATED TIMELINE

  • Design Schematics: May-June 2013
  • Development Permit Application: Mid-July 2013
  • Sales Launch: End of November 2013
  • Development Permit issued: Mid-February 2014
  • Building Permit issued: End of February 2014
  • Start demolition of existing building: End of February 2014
  • Start New Building Construction: Beginning of March 2014
  • estimated Construction Completion: April-May 2015

 